Digitization help student to explore and study their academic courses online, as this gives them flexibility and scheduling their learning at their convenience. Kidsfront has prepared unique course material of Quantitative Aptitude Work And Time for IBPS SO CWE Exam student. This free online Quantitative Aptitude study material for IBPS SO CWE Exam will help students in learning and doing practice on Work And Time topic of IBPS SO CWE Exam Quantitative Aptitude. The study material on Work And Time, help IBPS SO CWE Exam Quantitative Aptitude students to learn every aspect of Work And Time and prepare themselves for exams by doing online test exercise for Work And Time, as their study progresses in class. Kidsfront provide unique pattern of learning Quantitative Aptitude with free online comprehensive study material and loads of IBPS SO CWE Exam Quantitative Aptitude Work And Time exercise prepared by the highly professionals team. Students can understand Work And Time concept easily and consolidate their learning by doing practice test on Work And Time regularly till they excel in Quantitative Aptitude Work And Time.


Work And Time
A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?

a) 110
b) 75
c) 50
d) 100



Answer
Correct Answer Is : 110
Solution Is :
P can do a piece of work in 9 days. Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is

a) 3
b)
c)
d) 6



Answer
Correct Answer Is : 6
Solution Is :
Sixteen men can complete a work in fifteen years, twenty-four children can do the same work in twenty days. In how many days will eight men and eight children, complete the same work ?

a) 18days
b) 16days
c)
d) 20days



Answer
Correct Answer Is : 20days
Solution Is :
A tap drips at a rate of one drop/sec. 600 drops make 100ml. The number of litres wasted in 300 days is

a) 4320000
b) 432000
c) 43200
d) 4320



Answer
Correct Answer Is : 4320
Solution Is :
A can complete a work in days and B can complete it in ‘n days. How many days will it take to complete the work if both A and B work together ?

a) (m+n) DAYS
b) (1/m )*( 1/n) days
c) (m + n/ mn) days
d) (mn/ m + n) days



Answer
Correct Answer Is : (mn/ m + n) days
Solution Is :
A and B together can dig a trench in 12 days, which A can dig in 28 days; B aloone can dig it in

a) 20 days
b) 21 days
c) 22 days
d) 23 days



Answer
Correct Answer Is : 21 days
Solution Is :
A skilled, a half skilled and an unskilled labourer work for 7, 8 and 10 days respective;y and they together get Rs. 369 for their work. I the ratio of their each day`s work is 1/3:1/4:1/6, then how much thus the trained labourer get (in rupees)?

a) 164
b) 102.5
c) 201.5
d) 143.5



Answer
Correct Answer Is : 143.5
Solution Is :
A and B together can complete a piece of work in 12 days, B and C can do it in 20 days and C and A can do it in 15 days. A, B and C together can complete it in

a) 12 days
b) 6 days
c) 8 days
d) 10 days



Answer
Correct Answer Is : 10 days
Solution Is :
A and B together can complete a work in 3 days. They start together. But, after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in

a) 10 days
b) 4 days
c) 6 days
d) 8 days



Answer
Correct Answer Is : 6 days
Solution Is :
A does 20% less work than B. If A can complete a piece of work in 7.5 hours, then B can do it in

a) 10 hours
b) 4 hours
c) 6 hours
d) 8 hours



Answer
Correct Answer Is : 6 hours
Solution Is :